Now with respect to new network diagram value of cost slope are shown in following table: Here minimum value of cost slope is 45 for activity 5-6. Hence crashing activity 5-6 by 2 weeks from 6 weeks to 4 weeks. New network is shown in following fig: Since activity 5 – 6 is common in both critical paths, thus critical path will remain unchanged.